The EPA recently approved a demonstration project that uses phosphogypsum in road construction. The public comment period on the project is through Nov. 8th.
Comments can be submitted at https://www.regulations.gov under Docket ID No. EPA-HQ-OAR-2024-0446.
Phosphogypsum is the radioactive waste product left over from fertilizer production, and Florida has a lot of phosphogypsum.
High radionuclide levels, increased health risks, increased groundwater contamination and lack of state regulatory oversight are some of the many reasons why phosphogypsum should not be used in road construction.
The Environmental Protection Agency and other studies have previously determined that the use of radioactive phosphate gypsum wastes as building materials is unsafe and should not be done. This decision reflects the EPA's past concern that the radium-bearing waste, if spread throughout Florida, would present a public health threat that would continue for generations, given radium's 1,630-year radioactive decay half-life.
The lifetime cancer risk for adults resulting from exposure to this waste is one excess fatal cancer per 10,000 people. The risk for children is significantly higher.
Some elected officials are aiding the phosphate industry in their efforts to convince people that phosphogypsum will soon become an important asset in the form of material used for construction.
More stringent environmental regulation is needed to control the adverse impacts of phosphogypsum. Allowing the widespread distribution of phosphogypsum for road construction will lead to less oversight of a dangerous waste product. The EPA and the Florida Department of Environmental Protection lack adequate regulations needed to protect the public and the environment from hazards associated with gypsum stacks and the dispersal of phosphogypsum.
The distribution of phosphogypsum in road construction will unnecessarily expose workers, the environment, and the public to otherwise avoidable radiation exposure.
To allow the use of phosphogypsum as a construction material is the height of irresponsibility. Allowing phosphogypsum to be used for road construction will open the regulatory door for the use of phosphogypsum in construction or agricultural applications. The radioactive decay of this material will emit particles that can cause increased cancer risks and unacceptable radiation levels in areas that normally do not have such problems.
To date, no published scientific studies have confirmed that there is a "safe" industrial process to convert phosphogypsum for use in roads. All uses of phosphogypsum can cause significant health risks.
In addition to high radium 226 levels, central Florida phosphogypsum also contains significant amounts of sulfur and various heavy metals such as arsenic, barium, cadmium, and lead. Contaminated water and dissolved materials containing these toxins have the potential to seep from phosphogypsum used for construction purposes and pollute the underlying aquifer.
Phosphate companies have had more than 70 years to figure out a way to dispose of their radioactive gypsum wastes in an environmentally acceptable manner but have yet to do so. Instead, the industry produces tens of millions of tons of waste annually and continues expanding its dumping operations.
ManaSota-88 does not believe the phosphate industry should be permitted to externalize the costs of its phosphogypsum waste disposal problem at the public’s expense. The cost is too high. More stringent regulation is needed to control the adverse impacts of alternative uses of phosphogypsum, not only in the United States but worldwide.
Glenn Compton is the Chairman of ManaSota 88, a non-profit organization that has spent over 30 years fighting to protect the environment of Manatee and Sarasota counties.
1 comment on this item
Only paid subscribers can comment
Please log in to comment by clicking here.
WTF
Lets not forget. 10 years later they are still behaving badly not only in Florida but worldwide
Great facts by Craig Pittman
Craig Pittman Former Times Reporter
Published Oct. 2, 2015
Mosaic Fertilizer, the world's largest phosphate mining company, has agreed to pay nearly $2 billion to settle a federal lawsuit over hazardous waste and to clean up operations at six Florida sites and two in Louisiana, the Environmental Protection Agency announced Thursday.
"The 60 billion pounds of hazardous waste addressed in this case is the largest amount ever covered by a federal or state . . . settlement and will ensure that wastewater at Mosaic's facilities is properly managed and does not pose a threat to groundwater resources," the EPA said.
https://www.tampabay.com/news/environment/phosphate-giant-mosaic-agrees-to-pay-2-billion-over-mishandling-of/2247897/
Thursday, November 7 Report this