The Florida Department of Transportation has initiated construction on the $123 million Cortez Bridge replacement on State Road 684 in Manatee County. The project includes a new 65-foot-tall fixed-span bridge and roadway approaches from Gulf Drive to 123rd Street West, a distance of about 0.9 miles.
The bridge replacement project will be completed in two phases to maintain traffic throughout construction. During Phase 1, crews will construct the northern half of the new bridge alongside the existing bridge.
Once completed, traffic will shift to the new bridge. Phase 2 includes demolishing the existing bridge and constructing the remaining portion of the new bridge. Construction will use barges and temporary trestles in both phases.
Traffic Impacts
During Phase 1, traffic will be shifted slightly south at both bridge approaches. This shift will allow crews to build new roadway approaches and project features north of the existing roadway. Phase 1 also includes utility relocations and construction of the new Hunters Point Way connection.
The project is expected to last approximately 1,200 days. The phased construction approach is designed to minimize disruptions while delivering a new bridge and associated roadway improvements.